City Construction Projects

Construction Updates

Visit this page for construction and related notices for work occurring in San Dimas.

Note that while the City makes every attempt to provide you with the most up-to-date information, construction schedules may change with little or no notice for various reasons, including, but not limited to, weather conditions and unforeseen delays.  Thank you for your patience as we work together to improve the City of San Dimas!

  • Please click here for the most up-to-date information on the Foothill Gold Line.
  • Click here to view recently completed projects.

CC2025-04 East Fifth Street Et Al- Street Improvement Project

Construction Update 11/10/2025: 

The contractor has completed the PCC (concrete) work and will begin asphalt paving next. Vance Corporation plans to perform a 2-inch grind and pave, starting at Gladstone Street and Iglesias Street on November 12. Please note that the forecasted rain may delay the work schedule to the following week.

Construction Update 10/27/2025: 

The City's contractor, Vance Corporation will begin concrete (PCC) removal this week and plans to pour new concrete by the end of the week. Residents whose driveways are affected will be notified directly by the contractor.

Construction Update
10/22/2025: 

At the October 14, 2025 Council meeting, the City Council approved including Iglesia Street from Fifth Street to Bonita Avenue as part of the project. Residents whose address face Iglesia Street have been notified. 


Construction Update
10/13/2025:

Construction is scheduled to begin on October 20, 2025. The initial work will include potholing and locating existing utilities. During the following week, crews will begin removing concrete for sidewalks, curbs and gutters, and curb ramps.

Residents whose driveway access may be temporarily affected will receive advance notification from the contractor.

At the September 9th City Council Meeting, the City of San Dimas awarded a contract to Vance Corporation to rehabilitate the roadway on East Fifth Street (from San Dimas Avenue to Walnut Avenue), 500 & 600 Block of Belleview Avenue, Hallock Avenue, Payson Street (West of Walnut Avenue), Smead Way, and Gladstone Street (from Amelia Avenue to Dallas Road). The overall project is estimated to cost $900,000. The improvements will provide both an aesthetic enhancement to the neighborhood and improved access for residents.  Construction is scheduled to begin on October 20, 2025, and will take approximately two months to complete. Throughout construction, residents may experience changes to trash services and restricted access to driveways for short period. Also, the City will conduct inspections via drone to monitor progress of construction and completion of the project. For additional information, please contact the Public Works Department at (909) 394-6240 or publicworks@sandimasca.gov.

You may also contact the Project Contractor, Vance Corporation at (909) 355-4333.

Project Overview

The project will include rehabilitation of concrete curbs and gutters, along with asphalt pavement replacement, resulting in a smoother, quieter, and longer-lasting street surface. During construction, temporary traffic delays and lane restrictions should be expected.

Trash Services

 Waste Management has been directed to begin trash collection earlier than typically scheduled to avoid conflicts with construction activities.

Please place all bins out no later than 6:00 a.m. on scheduled pick-up days to avoid interruptions to service and construction. If you have any questions regarding additional trash services, please contact Public Works.

Driveway Access

In some cases, driveway access will be restricted between the hours of 7:00 a.m. and 5:00 p.m. for short durations. Residents will receive notification at least two days prior, whenever driveway access will be affected.

The City and its contractor will make every effort to minimize inconvenience, and your cooperation will help shorten the construction period and allow the City to restore normal traffic patterns as quickly as possible.

 Drone Inspections

As a courtesy, we would also like to inform you that between October and December 2025, the City’s licensed Unmanned Aircraft System (UAS) operator will be conducting operations with an FAA-registered drone in the project area. The drone will be used to capture before-and-after photographs and perform inspections related to the roadway improvements. Please be assured that your privacy is important, and the cameras will be focused solely on the roadway.
 While the construction impacts are temporary and inconvenient, its benefits are expected to last for decades to come. We would like to thank you in advance for your patience and cooperation during construction.
Gladstone St - Copy

Pic - Copy

 

San Dimas Assistant